2021/05/05www.unnouveauportpourcalais.com A great investment in the general interest of Calais, the local area, the Région and Europe… An economic and logistical stepping-stone for the future to adapt...
Deconstruction of the bridges Still a visible sign of the port transformation : early September, OAC1 and OAC2 steel decks between the Hoverport and the “Bassin Ravisse” were removed. Both...
Nearly 10 hectares reclaimed from the sea In July, the junction between the R3B cavalier and the breakwater created a basin. After this summer dredging, the basin is now almost filled and nearly 10...
2016/07/26Junction between the tempory breakwater and the breakwater After several weeks of work, the first junction point drawing the limits of the future port was finished, between the tempory breackwater parallel to the...
The Xblocs® factory in service Nearly 1 400 Xblocs of 4m3 (10 tons) were made in a few months by the factory located on the Hoverport site. This production allowed to wait for the Xblocs...
2016/06/30Starting building the breakwater Ground works started in spring. A 200 meter first section was built on the beach at low tide to close a first unit at its junction with the R3B cavalier...
2016/06/30The tempory breakwater In June 2016, the construction joint venture achieved a major step starting visually saving land on sea. The tempory breakwater was built a few meters away...
2016/06/03Noémie catching and realase On 29th April 2016, an operator working on Calais Port 2015 site, discovered a seal, wounded around the neck by a fishing net. Noémie Pruvost, Environmental...
2016/02/09The concrete plant in service The concrete plant is operational from the beginning of 2016. Everyone is impressed by its size : the plant will provide the main material for the works with...