2021/05/05www.unnouveauportpourcalais.com A great investment in the general interest of Calais, the local area, the Région and Europe… An economic and logistical stepping-stone for the future to adapt...
CALAIS PORT 2015 SECOND DREDGING CAMPAIGN The second dredging campaign in the basin began in March and will last from 2 to 3 months depending on the weather conditions. The Fernão de Magalhães dredger...
2017/03/14Calais Port 2015 has the "Chantier Bleu" Label The companions could be proud of them when raising the Chantier Bleu Label Flag on Tuesday 14th March. This symbolic event took place on Calais Port 2015 works...
2017/02/28A BIOHUT® IN THE MAISON DU PROJET ET DE L’EMPLOI Biodiversity is part of the Calais Port 2015 project environmental monitoring to have an improved compatibility between port infrastructures and marine...
The junction between the main breakwater and the Eastern inner embankment is now effective. As announced and in accordance with Calais Port 2015 schedule, the Eastern inner embankment and the main breakwater are now joined, creating the R4 basin to be...
PRODUCTION OF 6 M³ XBLOCS® HAS ALREADY STARTED Production of 4 m3 Xblocs® stopped on 25th January 2016. 4,056 Xblocs® of 4 m³ were produced of which 1,436 in the factory located on the Hoverport site...
2017/01/25The junction between the breakwater and the Eastern inner embankment is to be effective shortly… Works carried out by the Design and Construction Joint Venture progress on sea with the main breakwater now over 1 kilometer in length and the Eastern inner...
2017/01/25Covering the breakwater The weather is a significant factor to be considered in the construction of Calais Port 2015 breakwater. Due to sea state conditions, the work has regularly to...
2017/01/02One million tons transported by road At the very beginning of the year, materials provided by local quarries transported by road exceeded the one million tons.