Design and Construction JV living base
Concrete plant
Production of the first Xblocs in the factory operating with concrete trucks and manual formwork
The Xblocs® automated plant
The Xblocs® factory
Xblocs®
Geotechnical survey area
Surveyor
Infrastructure works
Aerial view of the Xblocs® factory and the concrete plant
Riprap first deliveries
Dredging and backfilling the cavalier
Dumper on the main breakwater
Works on the Eastern inner embankment
Jonction de la digue et du Pérré avant remblaiement
The first meters in sea of the breakwater
Dockside training
President François Hollande’s speech during Calais Port 2015 foundation stone-laying ceremony
Calais Port 2015 foundation stone-laying ceremony
Aerial view in December 2016
Covering the breakwater
Calais Port 2015 works site first visit
The Eastern inner embankment and the main breakwater in January 2017
The main breakwater in January 2017
Lifting the Blue Label flag at the life base
Dredging
Aerial view in April 2017
Backfilling
Aerial view of the dredger
Platforms
Works on section 3 of the breakwater
At the end of the main breakwater under construction
P10 ferry berth works on the Eastern inner embankment
A surveyor on the Eastern inner embankment
Pile driving activities at P10 berth
Site workers at P10 berth
View of the P10 berth and the main breakwater
Maritime works
Platform consolidation trough vibro flotation process
The main breackwater
Aerial view of the breakwater and the Earstern inner embankment
Aerial view of the Eastern inner embankment with the existing port in the background
General view
Platforms
Consolidation works around P10
The main breakwater
The main platform
Sunset on the construction site
No.2 engineering structure
The breakwater protection wall
The breakwater
Aerial view
The P10 first concrete beams
The breackwater is 250 meters long
Pre-loading on platforms
The basin taking shape
The ridge
Au loin les côtes anglaises
Diversion of the railway track
Work on the seawall
3.260 meters
View of the future extension of the port entrance
The central ridge
View on the breakwater
Aerial view of the site
The asphalt plant
Between two sea waters
A finger pier caisson
Ripraps arranged in spikes
Acces lanes to the port ring road
Summer 2019 aerial view
Maritime works
Works on the octopod
The central ridge - November 2019
The breakwater protection wall
Aeriel view of the site
The OA6 bridge
The building "Front de Mer"
The ferry berths
The arrival of the first link-span for vehicules
The breakwater end