2021/05/05www.unnouveauportpourcalais.com A great investment in the general interest of Calais, the local area, the Région and Europe… An economic and logistical stepping-stone for the future to adapt...
WORK PROGRESS ON BUILDINGS The Port Entrance Building is being erected. Gables of the building “Front de Mer” for passengers awaiting boarding are completed and the metal framework is...
THE P11 AND P12 FERRY PIER PROGRESS The construction of the P11/P12 pier is progressing. This set of 10 boxes for a total of 300 meters long is composed of 282 H profiles and 833 meters of sheet...
2019/12/03The latest Xblocs® This was one of the innovations that impressed so many people visiting the Calais Port 2015 site. After nearly 3 years in service , the Xblocs® plant...
Calais Port 2015 worksite visits To all interested persons in Calais Port 2015 project, visits are organized by the “Groupement Constructeur” design and construction joint venture...
THE END OF CALAIS PORT 2015 BRIDGES CIVIL ENGINEERING At the end of this 2019 summer, the Calais Port 2015 civil engineering teams have completed their work on bridges. The Design and Construction Joint Venture...
2019/09/02PROGRESS OF THE PROTECTION SEAWALL ON THE BREAKWATER This work progresses “backwards”, in other words it starts on a breakwater distant point to go back towards the land. And more precisely, 3 workshops are...
STARTING THE FOUNDATIONS WORK OF THE FIRST BUILDINGS The construction of the buildings has already started with the platforms preparation work for both emblematic buildings of the Port: the Port Entry Building...
2019/07/052019 OPEN DOORS DAY : ANOTHER GREAT SUCCESS! CALAIS PORT 2015 Design & Construction JV welcomed more than 200 visitors from 7 to 77 years old to its open day! A general presentation of the...